Question
Chapter 14, Problem 6P
Summary Introduction
Interpretation:
Whether
Concept Introduction:
Forward scheduling is the planning of the completion date for the task given. It is done when the task is to be started. Backward scheduling is the planning of the starting date for the task from the due date. It is done in the opposite direction of forward scheduling.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
When is Johnson’s rule best applied in job-shop scheduling?
Which aspects of Priority Scheduling are comparable to those of Shortest Job First Scheduling?
Using the FCFS rule for scheduling, the sequence is 1-2-3
For the schedule developed using the FCFS rule, the total length of time taken to
complete the three suits (including delivery) : hours (enter your response as a
whole number).
=
G
Sunny Park Tailors has been asked to make three different types of wedding suits
for separate customers. The table below highlights the time taken in hours for
cutting and sewing (process 1) and delivery (process 2) of each of the suits.
Times Taken for Different Activities (hours)
Cut and Sew
3
5
6
Suit
1
2
7
3
Deliver
4
2
∞ N
8
Assume that orders for suits have been listed in the above table in the order in
which they were received.
Chapter 14 Solutions
Practical Operations Management
Ch. 14 - Prob. 1DQCh. 14 - Prob. 2DQCh. 14 - Prob. 3DQCh. 14 - Prob. 4DQCh. 14 - Prob. 5DQCh. 14 - Prob. 1PCh. 14 - Prob. 2PCh. 14 - Prob. 3PCh. 14 - Prob. 4PCh. 14 - Prob. 6P
Ch. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - Prob. 15PCh. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Prob. 18PCh. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Prob. 23PCh. 14 - Prob. 24PCh. 14 - Prob. 25PCh. 14 - Prob. 26PCh. 14 - Prob. 27PCh. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Prob. 1.1QCh. 14 - Prob. 1.2QCh. 14 - Prob. 1.3QCh. 14 - Prob. 1.4Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Using the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery)= hours (enter your response as a whole number). Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Deliver Suit Cut and Sew 1 2 Assume that orders for suits have been listed in the above table in the order in which they were receivedarrow_forwardPriority Scheduling resembles Shortest Job First Scheduling in what ways?arrow_forwardWhat elements of Shortest Job First Scheduling and Priority Scheduling are comparable?arrow_forward
- Which simple scheduling concept can be applied to help schedule workers for a service operation with changing staffing requirements throughout the day?arrow_forwardWhat are the benefits and drawbacks of the shortest processing time rule (SPT)?arrow_forwardUsing the FCFS rule for scheduling, the sequence is Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including of the suits. delivery) = hours (enter your response as a whole number). Times Taken for Different Activities (hours) Deliver Suit Cut and Sew Using Johnson's rule for 2-machine scheduling, the sequence is 1 2. For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits 3 (including delivery) = hours (enter your response as a whole number). Assume that orders for suits have been listed in the above table in the order in which they were received. Of the two developed schedules, V rule gets the schedule finished sooner.arrow_forward
- A nursing home must schedule nurses in a manner that balances providing adequate patient care while keeping costs down. From historical records, administrators can project the minimum number of nurses to have on hand during each day/time slot. This data is shown below. Shift Time Slot Minimum number of nurses needed 1 12 am-4 10 2 4 am-8 6 3 8 am-12 8 4 12 pm-4 12 5 4 pm-8 10 6 8 pm-12 14 Nurses must start work at the beginning of one of the four-hour shifts (starting as early as 12 am midnight or as late as 8pm evening) and work for eight hours. Nurses who begin working at 8 pm will work until 4 am the next morning. Formulate and solve the nurse-scheduling problem so as to minimize excess stagging while satisfying minimum staffing requrements. What is the value of total excess staffing?arrow_forwardFive jobs are planned to be scheduled. Each of the jobs must be processed on three machines (A, B, and C) in the same order. The processing times are listed below. Use Johnson's Rule to determine the optimal sequence of jobs. Job B 16 10 11 10 14 20 12 3 10 8 4 1 O a) 3-1-2-4-5 O b) Johnson's Rule is not an Optimal Technique O c) 1-2-3-4-5 O d) 5-4-3-1-2 O e) 5-4-3-2-1 O) 5-4-2-1-3 O e) 5-4-2-3-1 2345arrow_forwardExplain why scheduling personnel in a service operation can be challenging.arrow_forward
- Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules: Job #151 was scheduled to begin on day 3 and to take 7 days. It got started on time and is 1 day ahead of schedule. Job #177 was scheduled to begin on day 3 and take 5 days. It is currently on time. Job #179 was scheduled to start on day 6 and take 3 days. It actually got started on day 5 and is progressing according to plan. Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected and should take 3 days. Job #215 was scheduled to begin on day 4 and take 5 days. It got started on time but has since fallen behind 2 days. This exercise contains only part a. a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual…arrow_forwardRon Satterfield's excavation company uses both Ganit scheduling charts and Gantt load charts. Today, which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules: Job #151 was scheduled to begin on day 3 and to take 5 days. It got started on time and is 1 day ahead of schedule. Job #177 was scheduled to begin on day 1 and take 4 days. It is currently on time. Job #179 was scheduled to start on day 6 and take 2 days. It actually got started on day 5 and is progressing according to plan. Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected and should take 3 days. Job #215 was scheduled to begin on day 5 and take 5 days. It got started on time but has since fallen behind 1 day. This exercise contains only part a a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual…arrow_forwardWhat do Priority Scheduling and Shortest Job First Scheduling have in common?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY