Question
Chapter 14, Problem 1.3Q
Summary Introduction
Case Summary:
Construction Company B was given the task to accomplish the roads of six locations before the winter starts. The company was given the additional task of removing the old road and reconstruct the new road. The process of removing the old road refers to the mailing and constructing of the new road refers to the paving.
Interpretation:
The actual paving would start its operations if Company B starts working from tomorrow onwards along with the number of days that will be required to accomplish all the projects once the paving operations start working.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Best-ride airlines that operates seven days a week has the following time-table.
Delhi - Mumbai
Mumbai - Delhi
Flight No
Departure
Arrival
1
7.00
8.00
2
8.00
9.00
3
13.00
14.00
4
18.00
19.00
Flight No
Departure
Arrival
101
8.00
9.00
102
9.00
10.00
103
12.00
13.00
104
17.00
18.00
Crews must have a minimum layover of 5 hours between flights. Obtain the pairing of flights that minimizes layover time away from home. For any given pairing, the crew will be based at the city that results in the smaller layover. For each pair also mention the city where crew should be based.
Four automobiles have entered Bubba’s Repair Shop
for various types of work, ranging from a transmis-sion overhaul to a brake job. The experience level of
the mechanics is quite varied, and Bubba would liketo minimize the time required to complete all of thejobs. He has estimated the time in minutes for eachmechanic to complete each job. Billy can completejob 1 in 400 minutes, job 2 in 90 minutes, job 3 in60 minutes, and job 4 in 120 minutes. Taylor willfinish job 1 in 650 minutes, job 2 in 120 minutes, job3 in 90 minutes, and job 4 in 180 minutes. Mark willfinish job 1 in 480 minutes, job 2 in 120 minutes, job3 in 80 minutes, and job 4 in 180 minutes. John willcomplete job 1 in 500 minutes, job 2 in 110 minutes,job 3 in 90 minutes, and job 4 in 150 minutes. Eachmechanic should be assigned to just one of these jobs.What is the minimum total time required to finish thefour jobs? Who should be assigned to each job?
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:
Job
processing time
hrs due from now
W
4
4
X
3
5
Y
2
2
Z
1
1
If he uses the earliest due date first priority rule to schedule these jobs, what will be the average job tardiness?
Chapter 14 Solutions
Practical Operations Management
Ch. 14 - Prob. 1DQCh. 14 - Prob. 2DQCh. 14 - Prob. 3DQCh. 14 - Prob. 4DQCh. 14 - Prob. 5DQCh. 14 - Prob. 1PCh. 14 - Prob. 2PCh. 14 - Prob. 3PCh. 14 - Prob. 4PCh. 14 - Prob. 6P
Ch. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - Prob. 15PCh. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Prob. 18PCh. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Prob. 23PCh. 14 - Prob. 24PCh. 14 - Prob. 25PCh. 14 - Prob. 26PCh. 14 - Prob. 27PCh. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Prob. 1.1QCh. 14 - Prob. 1.2QCh. 14 - Prob. 1.3QCh. 14 - Prob. 1.4Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- What potential problem might arise if time fences are not used? Why?arrow_forwardUsing the FCFS rule for scheduling, the sequence is Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including of the suits. delivery) = hours (enter your response as a whole number). Times Taken for Different Activities (hours) Deliver Suit Cut and Sew Using Johnson's rule for 2-machine scheduling, the sequence is 1 2. For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits 3 (including delivery) = hours (enter your response as a whole number). Assume that orders for suits have been listed in the above table in the order in which they were received. Of the two developed schedules, V rule gets the schedule finished sooner.arrow_forwardWhen selecting a web hosting company, one of the important factors to consider is uptime ratio. What is it, and why is it important?arrow_forward
- William Beebe owns a small shoe store. He has 10 pairs of shoes that requireresoling and polishing. He has a machine that can resole one pair of shoes at atime, and the time required for the operation varies with the type and condition of theshoe and the type of sole that is used. Shoes are polished on a machine dedi-cated tothis purpose as well, and polishing is always done after resoling. His assistant generally does the polishing while Mr. Beebe does the resoling. The resoling and polishingtimes (in minutes) are Shoes Resoling Time Polishing Time1 14 32 28 13 12 24 6 55 10 106 14 67 4 128 25 89 15 510 10 5In what order should the shoes be repaired in order to minimize the total makespanfor these 10 jobs?arrow_forwardEntriken Machinery specializes in developing weed-harvesting equipment that is used to clear small lakes of weeds. Dick Entriken, president of Entriken Machinery, is convinced that harvesting weeds is far better than using chemicals to kill weeds. Chemicals cause pollution, and the weeds seem to grow faster after chemicals have been used. Dick is contemplating the construction of a machine that could harvest weeds on narrow rivers and waterways. The activities that are necessary to build one of these experimental weed-harvesting machines are listed in the accompanying table. ---------------------------------------------- Activity Immediate Time (weeks) predecessor --------------------------------------------- A - 6 B - 5 C A 3 D A 2 E…arrow_forwardEntriken Machinery specializes in developing weed-harvesting equipment that is used to clear small lakes of weeds. Dick Entriken, president of Entriken Machinery, is convinced that harvesting weeds is far better than using chemicals to kill weeds. Chemicals cause pollution, and the weeds seem to grow faster after chemicals have been used. Dick is contemplating the construction of a machine that could harvest weeds on narrow rivers and waterways. The activities that are necessary to build one of these experimental weed-harvesting machines are listed in the accompanying table. ---------------------------------------------- Activity Immediate Time (weeks) predecessor --------------------------------------------- A - 6 B - 5 C A 3 D A 2 E…arrow_forward
- Entriken Machinery specializes in developing weed-harvesting equipment that is used to clear small lakes of weeds. Dick Entriken, president of Entriken Machinery, is convinced that harvesting weeds is far better than using chemicals to kill weeds. Chemicals cause pollution, and the weeds seem to grow faster after chemicals have been used. Dick is contemplating the construction of a machine that could harvest weeds on narrow rivers and waterways. The activities that are necessary to build one of these experimental weed-harvesting machines are listed in the accompanying table. ---------------------------------------------- Activity Immediate Time (weeks) predecessor --------------------------------------------- A - 6 B - 5 C A 3 D A 2 E…arrow_forwardEntriken Machinery specializes in developing weed-harvesting equipment that is used to clear small lakes of weeds. Dick Entriken, president of Entriken Machinery, is convinced that harvesting weeds is far better than using chemicals to kill weeds. Chemicals cause pollution, and the weeds seem to grow faster after chemicals have been used. Dick is contemplating the construction of a machine that could harvest weeds on narrow rivers and waterways. The activities that are necessary to build one of these experimental weed-harvesting machines are listed in the accompanying table. ---------------------------------------------- Activity Immediate Time (weeks) predecessor --------------------------------------------- A - 6 B - 5 C A 3 D A 2 E…arrow_forwardChristine has three cars that must be overhauled by her ace mechanic, Megan. Given the following data about the cars, use least slack per remaining operation to determine Megan’s scheduling priority for each:Customer Pick-Up Remaining Overhaul Car Time (hours hence) Time (hours) Remaining Operation A 10 4 PaintingB 17 5 Wheel alignment, painting C 15 1 Chrome plating, painting, seat repairarrow_forward
- Understanding that, in the three-time estimate approach, the time to complete an activity is assumed to follow a Beta distribution. Write the formula illustrated in the text.arrow_forwardThe following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.arrow_forwardWhy is managing bottlenecks so important in work center scheduling?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY