Question
Chapter 14, Problem 9PA
Summary Introduction
Interpretation: The schedule that should be adopted by the M and if M will be able to complete all the work jobs is to be discussed.
Concept Introduction: Sequencing and
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Thomas has four assignments due in class tomorrow, and his class times are as follows.
Class
Time
Marketing 304
8 am
OM 385
10 am
Finance 216
2 pm
Psychology
4:30 pm
Each class lasts one hour, and Thomas has no other classes. It is now midnight, and Thomas estimates that the marketing, OM, finance, and psychology assignments will take him six, three, four, and two hours, respectively.
Use the Excel Sequencing template to determine how he should schedule the work. Can he complete all of it on time?
(Hint: Using SPT and EDD. First, convert times to due dates past midnight).
Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end
of day 7, Ron is reviewing the Gantt chart depicting these schedules:
Day
Job #151 was scheduled to begin on day 3 and to take 6 days. It got started on time and is 1 day ahead of schedule.
Job #177 was scheduled to begin on day 1 and take 4 days. It is currently on time.
Job #179 was scheduled to start on day 7 and take 2 days. It actually got started on day 6 and is progressing according
to plan.
Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected
and should take 3 days.
Job #215 was scheduled to begin on day 4 and take 5 days. It got started on time but has since fallen behind 2 days.
Job 12 3 4 56 789 10 11
--
151
177 +
This exercise contains only part a.
179
a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already
plotted). Using the line…
Ron Satterfield's excavation company uses both Ganit scheduling charts and Gantt load charts. Today,
which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules:
Job #151 was scheduled to begin on day 3 and to take 5 days. It got started on time and is 1 day ahead of
schedule.
Job #177 was scheduled to begin on day 1 and take 4 days. It is currently on time.
Job #179 was scheduled to start on day 6 and take 2 days. It actually got started on day 5 and is
progressing according to plan.
Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing
as expected and should take 3 days.
Job #215 was scheduled to begin on day 5 and take 5 days. It got started on time but has since fallen
behind 1 day.
This exercise contains only part a
a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have
been already plotted as blue lines).
Using the line drawing tool, plot the actual…
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today, which is the end of day 7, Ron is reviewing the Gantt chart depicting these schedules: Job #151 was scheduled to begin on day 3 and to take 7 days. It got started on time and is 1 day ahead of schedule. Job #177 was scheduled to begin on day 3 and take 5 days. It is currently on time. Job #179 was scheduled to start on day 6 and take 3 days. It actually got started on day 5 and is progressing according to plan. Job #211 was scheduled to begin on day 5, but missing equipment delayed it until day 6. It is progressing as expected and should take 3 days. Job #215 was scheduled to begin on day 4 and take 5 days. It got started on time but has since fallen behind 2 days. This exercise contains only part a. a) Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines). Using the line drawing tool, plot the actual…arrow_forwardA nursing home must schedule nurses in a manner that balances providing adequate patient care while keeping costs down. From historical records, administrators can project the minimum number of nurses to have on hand during each day/time slot. This data is shown below. Shift Time Slot Minimum number of nurses needed 1 12 am-4 10 2 4 am-8 6 3 8 am-12 8 4 12 pm-4 12 5 4 pm-8 10 6 8 pm-12 14 Nurses must start work at the beginning of one of the four-hour shifts (starting as early as 12 am midnight or as late as 8pm evening) and work for eight hours. Nurses who begin working at 8 pm will work until 4 am the next morning. Formulate and solve the nurse-scheduling problem so as to minimize excess stagging while satisfying minimum staffing requrements. What is the value of total excess staffing?arrow_forwardAn independent accountant is planning to prepare tax returns for six of her clients.Prior to her actually preparing each return, her secretary checks the client’s file to besure all the necessary documentation is there and obtains all the tax forms needed forthe preparation of the return. Based on past experience with the clients, her secretaryestimates that the following times (in hours) are required for preparation of the returnand for the accountant to complete the necessary paperwork prior to filing each return:Client Secretary Time Accountant Time1 1.2 2.52 1.6 4.53 2.0 2.04 1.5 6.05 3.1 5.06 0.5 1.5In what order should the work be completed in order to minimize the total timerequired for all six clients?arrow_forward
- Using the FCFS rule for scheduling, the sequence is Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including of the suits. delivery) = hours (enter your response as a whole number). Times Taken for Different Activities (hours) Deliver Suit Cut and Sew Using Johnson's rule for 2-machine scheduling, the sequence is 1 2. For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits 3 (including delivery) = hours (enter your response as a whole number). Assume that orders for suits have been listed in the above table in the order in which they were received. Of the two developed schedules, V rule gets the schedule finished sooner.arrow_forwardThe owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Job processing time hrs due from now W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the earliest due date first priority rule to schedule these jobs, what will be the average job tardiness?arrow_forwardUsing the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) : hours (enter your response as a whole number). = G Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Cut and Sew 3 5 6 Suit 1 2 7 3 Deliver 4 2 ∞ N 8 Assume that orders for suits have been listed in the above table in the order in which they were received.arrow_forward
- A mortgage service office has the following four activities involved in approving a loan application. Note that a working day is 8 hours and there are 60 minutes in one hour. Activity Time (minutes) A. Property survey 24 B. Credit report 19 C. Title search 18 D. Final decision 20 The office has three employees, activities A, B and C are combined together and assigned to two employees, while the other employee is responsible for the last activity D. Under this setting, what would be the maximum number of loan applications the office can process per day? Numbers only, keep three decimals if not exact, either round up or down is okarrow_forwardUsing the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery)= hours (enter your response as a whole number). Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Deliver Suit Cut and Sew 1 2 Assume that orders for suits have been listed in the above table in the order in which they were receivedarrow_forwardThe owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Job W X Y Z Processing Time (hrs) 4 3 2 1 Multiple Choice If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average completion time? O 7.5 hours 5 hours 3 hours 2.5 hours Due (hrs from now) 4 2 hours 5 2 1arrow_forward
- When is Johnson’s rule best applied in job-shop scheduling?arrow_forwardCollege students always have a lot of work to do, but thissemester, Katie Lawrence is overwhelmed. Following arethe assignments she faces, the estimated completion times(in days), and due dates:Help Katie prioritize her work so that she completes asmany assignments on time as possible. Today is November2. How would your sequence of assignments change ifKatie were interested in minimizing the mean tardiness ofher assignments?arrow_forwardWood Log Company has forecasted the demand for wooden log for next month. The company has listed the processing time, and the due date for each task to produce wood log as follows t; (days) d, (days) 1 3 7 3 5 7 14 5 25 7 19 10 39 12 18 15 25 10 18 40 The company wants to minimize the average flow time. What will be the sequence and schedule, makespan, average flow time, average lateness, and how many tardiness if: a. The company have machine to process the wood b. The company have 2 machine to process the wood 6 7. 4)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY