Question
Chapter 14, Problem 8PA
Summary Introduction
Interpretation: the average flow time after every job is completed, tardiness, and lateness individually for SPT sequence, EDD sequence and for the sequence of 2-1-5-3-4 is to be calculated based on the given information.
Concept Introduction: The process of planning the ordering of the activities involves based on the elements such as, priority, set up time and such other is referred to as sequencing.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The first five columns of the following table contain information about a set of four jobs that just arrived (end of Hour 0 or beginning of Hour 1) at an engine lathe. They are the only ones now waiting to be processed. Several operations, including the one at the engine lathe, remain to be done on each job. Determine the schedule by using (a) the CR rule and (b) the S/RO rule. Compare these schedules to those generated by FCFS, SPT, and EDD.
Job
ProcessingTime at EngineLathe (hours)
TimeRemainingUntil Due Date(days)
Number ofOperationsRemaining
Shop TimeRemaining(days)
CR
S/RO
1
2
3
4
2.3
10.5
6.2
15.6
15
10
20
8
10
2
12
5
6.1
7.8
14.5
10.2
2.46
1.28
1.38
0.78
0.89
1.10
0.46
-0.44
An insurance claims work area has five claims waiting for processing as follows:
Job
Processing Time
Due Date (Di )
1
18
31
2
14
25
3
12
23
4
19
24
5
10
37
Use the Excel Sequencing template to find the average flowtime, average and maximum tardiness, and average lateness for the following sequences: SPT sequence, EDD sequence, and the sequence 4-3-2-1-5. Round your answers for the average values to two decimal places.
The SPT sequence is - - - - .
Average Flow Time
Average Tardiness
Maximum Tardiness
Average Lateness
The EDD sequence is - - - - .
Average Flow Time
Average Tardiness
Maximum Tardiness
Average Lateness
4-3-2-1-5 sequence:
Average Flow Time
Average Tardiness
Maximum Tardiness
Average Lateness
What sequencing rule do you recommend?
The ___________ is recommended as it minimizes average flow time and number of jobs in system.
The following jobs are waiting to be processed at Jeremy LaMontagne's machine center. Today is day 250. Using the critical ratio scheduling rule, in what sequence would the jobs be processed?
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following jobs are waiting to be processed atJeremy LaMontagne’s machine center. Today is day 250. Using the critical ratio scheduling rule, in what sequencewould the jobs be processed?arrow_forwardThe data for five tax analysis jobs waiting to be processed by Martha at T. R. Accounting Service has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below. Questions 1. Use the shortest-processing-time (SPT) sequencing rules to sequence the jobs. Compute the flow time, tardiness, and lateness for each job, and the average flow time, average tardiness, and average lateness for all jobs. Use minus sign to enter negative lateness values, if any. Round the average values to two decimal places. Sequence Job Processing Time Due Date Flow Time Lateness Tardiness 1 2 3 4 5 Average 2. Use the earliest-due-date (EDD) sequencing rules to sequence the jobs. Compute the flow time, tardiness, and lateness for each job, and the average flow time, average tardiness, and average lateness for all jobs. Use minus…arrow_forwardin a short essay explain the advantages and disadvantages of shortest processing time (SPT) and earliest due date (EDD) sequencing rules. Under what circumstances might you prefer one over the other?arrow_forward
- The following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.arrow_forwardWhat are the benefits and drawbacks of the shortest processing time rule (SPT)?arrow_forwardApply the four popular sequencing rules to the five jobs shown in the table below. For each sequence determine: The average completion time (sum of total flow time/number of jobs) Utilisation measure (Total job work time/Sum of total flow time) Average number of jobs in system (Sum of total flow time/Total job work time) Average job lateness (Total late days/Number of jobs) Job Due Job Work (Processing) Time Date (Days) (Days) 8 6 18 15 23 Job ABCDE 6 W ∞ NO 6 2 8 3 9arrow_forward
- Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): Sequence 1 Job The following jobs are waiting to be processed at Rick Solano's machine center. Solano's machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled today, which is day 241 (day 241 is a work day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. 2 3 4 5 ... The total flow time for the sequence developed using the SPT rule = days (round your response to two decimal places). The percentage utilization for the sequence developed using the SPT rule = ☐ % (enter your response as a percentage rounded to two decimal places). The average number of jobs in the system for the sequence developed using the SPT rule = jobs (round your response to two decimal…arrow_forwardThe following jobs are waiting to be processed at a small machine center: DUE DATE 250 242 250 260 265 JOB 10 20 30 40 50 DURATION (DAYS) 20 10 16 34 6 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a) Sequence the jobs according to LPT. According to the LPT rulle, the sequence of jobs should be b) What is the average completion (flow) time? The average completion (flow) time is c) What is the average job lateness? The average job lateness is d) What is the average number of jobs in the system? The average number of jobs in the system is jobs (round your response to one decimal place). days (round your response to one decimal place). days (round your response to ane decimal place).arrow_forwardThe following five overhaul jobs a re waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days.Assume that all jobs arrived on day 180; today's date is 200 Using the critical ratio scheduling rule, in what sequence would the jobs be processed?arrow_forward
- In her last semester at SPC, Polly Hedron needs to take Statistics, Composition 2, and Ethics. Because Polly is registering early, she has 17 choices for her section of Statistics, 11 choices for her section of Composition, and 19 choices for her section of Ethics. From how many possible schedules can Polly choose? (You may presume that none of these sections interfere with each other) Your Answer:arrow_forwardThe following jobs are waiting to be processed at thesame machine center. Jobs are logged as they arrive:JOB DUE DATE DURATION (DAYS)A 313 8B 312 16C 325 40D 314 5E 314 3 In what sequence would the jobs be ranked according to the follow-ing decision rules: (a) FCFS, (b) EDD, (c) SPT, and (d) LPT? All dates are specified as manufacturing planning calendar days. Assumethat all jobs arrive on day 275. Which decision is best and why?arrow_forwardDe Law Construction has a gotten some construction jobs to build some starter housing units in a few areas. The building time for each housing unit to be completed as well as the date that each unit is to be completed is shown in the table below. Today is Day 471. Which of the sequences, EDD OR SPT should the company use to sequence the order in which they do the jobs, assuming that because of resource constraints it cannot do the jobs simultaneously? HOUSING UNIT Building Time (days) Due Date Marabella 39 Day 502 Tabaquite 23 Day 528 San Juan 30 Day 515 Mayaro 33 Day 498 D’Abadie 41 Day 535 Preysal 40 Day 510 Some time after starting the jobs according to the sequence you decided on, it was found that because of inclement weather the last three housing units in the sequence have been delayed. You now have to prioritise and decide in which order to expedite those three jobs, using the Critical Ratio model. It is now…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY