Power System Analysis and Design (MindTap Course List)
Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN: 9781305632134
Author: J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher: Cengage Learning
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 6, Problem 6.30P

Determine the bus admittance matrix ( Y bus ) for the three-phase power system shown in Figure 6.23 with input data given in Table 6.11 and partial results in Table 6.12. Assume a three-phase 100 MVA per unit base.

Chapter 6, Problem 6.30P, Determine the bus admittance matrix (Ybus) for the three-phase power system shown in Figure 6.23 , example  1

TABLE 6.11

Bus input data for Problem 6.20

Chapter 6, Problem 6.30P, Determine the bus admittance matrix (Ybus) for the three-phase power system shown in Figure 6.23 , example  2

TABLE 6.12

Partially Completed Bus Admittance Matrix ( Y bus ) for Problem 6.30

Blurred answer
Students have asked these similar questions
Figure 6.12 shows the one-line diagram of a simple three-bus power system with generators at buses 1 and 3. The magnitude of voltage at bus 1 is adjusted to 1.05 pu. Voltage magnitude at bus 3 is fixed at 1.04 pu with a real power generation of 200 MW. A load consisting of 400 MW and 250 Mvar is taken from bus 2. Line impedances are marked in per unit on a 100 MVA base, and the line charging susceptances are neglected. Obtain the power flow solution by the Gauss-Seidel method including line flows and line losses. 1 2 0.02 + j0.04 400 MW 0.01 + j0.03 0.0125 + j0.025 250 Mvar Slack Bus 3 V = 1.0520° 200 MW | V3 = 1.04 Figure 6.12
6.1. A power system network is shown in Figure 47. The generators at buses 1 and 2 are represented by their equivalent current sources with their reactances in per unit on a 100-MVA base. The lines are represented by n model where series reactances and shunt reactances are also expressed in per unit on a 100 MVA base. The loads at buses 3 and 4 are expressed in MW and Mvar. (a) Assuming a voltage magnitude of 1.0 per unit at buses 3 and 4, convert the loads to per unit impedances. Convert network impedances to admittances and obtain the bus admittance matrix by inspection. j0.25 50.25 -j4 j0.4 j0.1 j0.16 j0.2 -j4+3 4 S3 -j4 S4 FIGURE 47 One-line diagram for Problem 6.1. 100 MW +j25 Mvar 200 MW +j50 Mvar
6.32 For a two-bus power system, a 0.7 + j0.4 per unit load at bus 2 is supplied by a generator at bus 1 through a transmission line with series impedance of 0.05 + j0.1 per unit. With bus 1 as the slack bus with a fixed per-unit voltage of 1.0/0, use the Gauss-Seidel method to calculate the voltage at bus 2 after three iterations.
Knowledge Booster
Background pattern image
Electrical Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Text book image
Power System Analysis and Design (MindTap Course ...
Electrical Engineering
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:Cengage Learning
How do Electric Transmission Lines Work?; Author: Practical Engineering;https://www.youtube.com/watch?v=qjY31x0m3d8;License: Standard Youtube License