In the following table the activities with their precedence sequence and expected time (days) are listed a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor Time (day s) 33 44 66 66 44 44 66 88 ABCDEFGH (s) Figure 1 - A A B B C D E, F The correct AON diagram for the project is: Figure 3 E Figure 2 H
Q: Suppose Mr. North randomly selected University in the country and then randomly selected Botswana…
A: The objective of the question is to identify the type of sampling technique used by Mr. North in his…
Q: Explain which types of expatriate compensation packages are most beneficial to the employee and…
A: The objective of this question is to understand the types of expatriate compensation packages that…
Q: The information below shows the order in which the activities of a project occur along with the time…
A: Table is:Now, I would prepare the network diagram using the above dataset,
Q: Priority-Discipline Queueing Models Southeast Airlines is a small commuter airline serving primarily…
A:
Q: Which of the following is true of short and simple words? They should be…
A: The question is asking us to identify the correct statement about the use of short and simple words…
Q: How would you write the optimal solution for these?
A: Let me state given the table data,…
Q: Describe transformational leadership. What are the four types of leadership behaviors that are…
A: Transformational leadership is a style of leadership where a leader works with subordinates to…
Q: 37. Purchasing is a functional subsystem of the foodservice organization. Identify what signals in…
A: When it comes to managing the ever-changing process of purchasing products, services, or manpower…
Q: Customers enter the camera department of a store at an average rate of six per hour. The department…
A: The given problem corresponds to the M/M/1 queuing model which is a single-server queuing system…
Q: Which of the following is not a form of measurement validity? a) Concurrent validityb) Conductive…
A: The objective of the question is to identify the term that does not represent a form of measurement…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: The objective of the question is to determine the project length, total cost, the activity to be…
Q: • 12.10 Matthew Liotine's Dream Store sells beds and as- sorted supplies. His best-selling bed has…
A: Annual Demand = 400 unitsOrdering Cost = $40Holding Cost = $5 per unit per year
Q: Network Analysis Given this WBS, draw out a network diagram and use the two-pass and enumera methods…
A: The objective of this question is to determine the critical path for the project based on the given…
Q: Jitsmsmart is a retailer of plastic action-figure toys. The action figures are purchased from Tacky…
A: Find the given details below:
Q: Why is the Medicare system always changing and evolving? (Select all that apply) More people are…
A: The Medicare system, established in 1966, has undergone numerous changes and adaptations over the…
Q: No AI pls True or false? Operations management is focused primarily on the application of…
A: To generate goods and services, processes, resources, and systems must be managed effectively. This…
Q: Consider a production process described by the following flowchart, on which the process time of…
A: Given, a production process flowchart.Station Station Station The fixed cost for building the…
Q: A toll tunnel has decided to experiment with the use of a debit card for the collection of tolls.…
A: Arrival rate = 750 per hourservice rate = In hour, = 900 per hour
Q: In regards to the OPCF 43 limited waiver of depreciation endorsement, what is the insured NOT…
A: The Limited Waiver of Depreciation Endorsement is a type of add-on coverage that can be included in…
Q: particular forecasting mode and actual demands that resulted: April May June July August September…
A: The accuracy of a forecast is measured using various metrics. Some of them are MAD, MAPE, Mean…
Q: Henrique Correa's bakery prepares all its cakes between 4 A.M.and 6 A.M.so they will be fresh when…
A: Cs=Sales price per unit−Cost per unit = 8-5 = 3Co=Cost per unit−Salvage value per unit…
Q: explain the key components of operations planning in a manufacturing environment.
A: Operations planning is a critical aspect of manufacturing management, involving the strategic…
Q: Examine the impact of occupational diseases, stress and communicable diseases to the health and…
A: Maintaining workers' health and safety in today's changing work conditions is critical to the…
Q: How does the integration of product development within operations management frameworks contribute…
A: Operation management is an aspect of management that deals with the management of the production,…
Q: You are leading your organization's effort to purchase and install new accounting software. The…
A: Business ethics is the aspects of business that define the standards or directives that assist in…
Q: A firm has recently added a new product to their offerings. Manufacturing reports that production is…
A: According to the given information, the firm added new products to their offerings. Now, the…
Q: Centerville Bikes and Stuff (CBS) sells motorcycles and accessories. The number of helmets sold by…
A: Answers are given below:Explanation:Answers:a) What type of pattern exists in data?Answer: The data…
Q: how does the project life cycle contribute to effective resource management and budget control?
A: The project life cycle refers to the stages of a project that must be completed efficiently. It…
Q: IIn a job shop, effective capacity is only 69 percent of design capacity, and actual output is 76…
A: Capacity management is the aspect of production management that specifies the maximum or highest…
Q: Acme Block Company has orders for 80 tons of concrete blocks at three suburban locations as follows:
A: A transportation problem refers to a specific type of linear programming problem where the objective…
Q: Hi! I need a little help with D. I can't figure out how to calculate the efficiency. Can you explain…
A: The efficiency of the balanced line is approximately 63.89%.Explanation:1. Total Task Times: This is…
Q: how does the project life cycle influence resource allocation and utilization?
A: The project life cycle represents the stages a project progresses through from initiation to…
Q: Operation management... discuss , what role does supply chain resilience play in mitigating…
A: Operation management is an aspect of management that deals with the management of the production,…
Q: A company has three warehouses that supply four stores with a given product. Each warehouse has 30…
A: Find the given details below:Note that we could not solve the first condition through the solver…
Q: How do organizations measure and track the effectiveness of their Quality Assurance programs?
A: The goal of quality assurance as a business idea is to provide value for customers by removing…
Q: . What are the characteristics of a successful product differentiation strategy?
A: A successful product differentiation strategy is vital for businesses seeking to distinguish their…
Q: Draw up a flow chart of the operations needed to make an ashtray. Call each operation by name
A: Creating an ashtray involves a series of meticulous operations, each contributing to the final…
Q: Alaskan Railroad is an independent, stand-alone railroad opertaon not connected to any other rail…
A: Find the given details below:10 - dummy line (place)
Q: A study-aid desk staffed by a graduate student has been established to answer students' questions…
A: Shift = 8 hrs. per dayArrival rate = 4 per hourAssistance (service) time = 10 minutesAssume…
Q: with the information given draw a graph, On the x-axis, you would have the number of units sold…
A: First, I will do the spreadsheet calculations, Here, for a specific number of units sold, I will…
Q: For the lincar programming problem below, using simplex method to maximize: Z= x₁ + 2x₂ + 4x₂…
A: Linear Programming Problem is given below:
Q: ou have just started work as the Supply Chain Manager for Skateboards company These powered skate…
A: Supply chain management is the aspect of management that deals with all the movement or flow that…
Q: You are getting into a business and want to take a loan. The bank requires that you show them your…
A: The objective of this question is to develop a five-year financial forecast showing profits before…
Q: When referencing other works you have cited within the text of the report you shoulda) State the…
A: The objective of the question is to identify the correct method of referencing other works within…
Q: PART Frame WC200 Week MPS A WC300 B WC300 Total с D WC400 WC500 -3 Past Due -2 -1 0 1 20 2 30 3 35 4…
A: 1# Define the production schedule and work center details extracted and parsed from the OCR output…
Q: Chicago's Hard Rock Hotel distributes a mean of 1,200 bath towels per day to guests at the pool and…
A: Mean demand per day (AVG) = 1200 towelsStandard deviation of demand per day (STD)= 95 towels Lead…
Q: The planned weekly demand for new components from a German manufacturer is 5,000 units. The standard…
A: Weekly demand = 5000 unitsCost per unit = $10Holding cost rate = 30%Target Service Level (TSL) =…
Q: In what ways can a well-designed layout strategy contribute to minimizing material handling costs…
A: Layout design has strategic implications since it establishes an organization's competitive…
Q: Alpha Sennon | Ashoka | Everyone a Changemaker Identify and discuss at least 4 Characteristics and…
A: Alpha Sennon exemplifies the traits and skill sets commonly associated with successful social…
Q: What is throughput time of this process? A 12.8 min B 10.75 min C 19.00 min D 31.00 min E 22.50 min
A:
Trending now
This is a popular solution!
Step by step
Solved in 1 steps
- Normal Time Problem 1 You are the manager of a project to improve a billing process at your firm. The following table contains the data you will need to conduct crashing of the project duration. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after Week 12. Activity Immediate Predecessor(s) Crash Time (weeks) Normal (Direct) Cost Crash Cost (weeks) ($) ($) A 4 1 5,000 8,000 B 5 2 8,000 11,000 C A 1 1 4,000 4,000 Ꭰ B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F Ꭰ 7 6 4,000 7,000 What is the optimum choice for project duration?The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS ACTIVITY A ABCDEFGH B-E-G-H b. What is the critical path? A-C-F-H OA-D-F-H A-D-G-H A A B C,D D, E F,G Project completion time a LLL23312 TIMES (DAYS) m •WNNW: 3 2 2 3 4 4 4 4 b 5 3 3 4 11 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. days 565The following Table 1 contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis. Table 1 Activity Predecessor Crash Time Normal Cost (Weeks) Normal Time Crash Cost (Weeks) $ A 10 7 2000 2600 A 12 1500 2000 C A 16 12 2200 300 D 8 7 2500 3000 E C 13 10 1950 2275 F D 9. 8 800 1000 G E, F 24 29 3650 4000 H G 17 14 1200 1800 a) Determine the project cost and duration without crashing. b) Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration. c) Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.
- Draw the PDM network diagram for the following project, calculate the earliest and latest starting and finishing times for all activities, and hence calculate the total float, free float for each activity. Activity IPA Duration (WEEKS) WORKERS REQUIRED PER WEEK EQUIPMENT REQUIRED (hrs/WEEK) H ---- 10 5 8 I H 8 4 2 J H 6 8 6 K J 4 2 1 L J 2 6 2 M J 4 3 2 N I 4 2 0 O I 5 5 0 P I, J 5 6 6 Q L 5 2 0 R M 5 0 4 S N 3 0 4 T Q 3 0 0 U O, S 1 9 8 V K, R 5 14 8 W U 2 6 8 X V 3 6 8 Y P,W,X,T 8 14 8 Z Y 6 5 8 If there is a limit of 15 workers per week, smooth the workers loading using ES and LS histogram. Based on the proposed scheduling, plot the equipment loading histogram for the project. Independently of the above resource leveling, schedule the…Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) Activity Preceded 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts Software development 5 6 Manufacture custom parts 7 Assemble 8 Test Duration 5 15 20 13 18 10 10 5 1 1 1 4 2,3,6 2,5 Resources Ryan Carly Ryan Lauren Connor Ryan Dawn Test Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).The following Table 1 contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis. Table 1 Activity Activity Predecessor A B с D E F G H --- A A B B с D, E Activity Time (weeks) Normal 16 14 8 5 4 6 10 15 Crash 8 9 6 4 2 4 7 10 Activity Cost (S) Normal 2,000 1,000 500 600 1,500 800 3,000 5,000 Crash 4,000 1,800 700 1,300 3,000 1,600 4,500 8,000 a) Determine the project cost and duration without crashing. b) Determine the least expensive project cost if the duration is to be crashed by two weeks. c) Determine the least expensive project cost if the duration is to be crashed to 28 weeks.
- Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 44 B Develop Client Prospectus ― 35 C Perform Design Analysis ― 46 D Program Back End A, B, C 43 E Program Front End A 27 F Project Consolidation D, E 36 (a) For the given project, fill in the nodes of the network diagram below. A E 44 27 Start B D F Finish Time 35 43 36 Time C 46 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 33 B Develop Client Prospectus ― 21 C Perform Design Analysis ― 35 D Program Back End A, B, C 47 E Program Front End A 13 F Project Consolidation D, E 11 (a) For the given project, fill in the nodes of the network diagram below. A E 33 13 Start B D F Finish Time 21 47 11 Time C 35 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…Consider the following project network and activity times (in days). E Start Finish D F G Activity | A B C D EF G Time 3 5 6 .2 The crashing data for this project are as follows: Time (days) Cost ($) Activity Normal Crash Normal Crash 800 1,200 2,000 A 2 1,400 В 2 1 1,900 3 2,800 1,500 1,800 2,300 E 6 4 2,800 1,000 1,000 F 2 1 600 G 2 1 500 a. Find the critical path and the expected project completion time. b. What is the total project cost using the normal times? Assume that management desires a 12-day project completion time. c. Formulate a linear programming model that can be used to assist with the crashing decisions. d. What activities should be crashed? e. What is the total project cost for the 12-day completion time? 2.
- Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity A B C D E F G H IMG_A2D52FAF8F3D-1.jpeg Activity This answer has not been graded yet. A B с (c) Develop the activity schedule for the project. D Survey building site Develop initial design Obtain board approval E F G Description H Select architect Establish budget Finalize design Obtain financing 0 Hire contractor L L | (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen Immediate Predecessor Earliest Start (b) Identify the critical path. (Enter your answers as a comma-separated list.) 4 A, B с Latest Start с D, E E F, G Time (weeks) 5 5 9 Earliest Finish 13 4 7 15 11 6 9 Latest Finish 4 Slack (d) Does it appear…Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______Activity A B CDEFG 3. You have been appointed as the project leader of a project to be undertaken by your company. You have identified the following tasks and made the time estimates for each task as listed in the table below: с Preceding "from" activity A A A B,C C,D,E F Succeeding "to" activity B,C,D E E F F G Estimated duration work days) 3 5 3 10 8 14 7 a) Use the above table to construct a project network diagram. b) Determine the critical path for the project and its duration.