the production manager of a company has o decide l operate an automatic machine in the place of a semi autonmatic machine The following data is available Date Automatic Semiautonmate Time for the job 2 min 5 min Set up time 2 hrs 1.5 hrs Cost/hr 320 {12 The quantity of production above which the automatic machine is prolitable is (A) 72 (B) 70 (C) 66 (D) 52
Q: What are the first two areas that should be identified in value stream mapping? (Choose two.)
A: 1st two areas are: The Steps The Bottlenecks
Q: A fast moving item has a demand of 18000 units/year. The cost of one procurement is Rs. 50 and…
A:
Q: Detail drawings are drawings of each part contained in the assembly of a product. The only parts…
A: Given Engineering details drawing AUTOCAD To find Not included in Engineering details drawing…
Q: A certain job shop specializes in one-of-a-kind orders dealing with parts of medium-to-high…
A: Given Eight conventional machine tool To find Present machine lead time New machine lead time…
Q: B. A Highway Engineer tabulates the following ADT for the Highway that will be constructed. the…
A: AADT* k factor = hourly volume design The k factor is the hourly volume adjustment factor for the…
Q: Q5- put a/an before the count nouns, and some before the un-count nouns. 1- A chair 2- --- petrol 3-…
A: A count noun is a noun that something countable. For example, A man, tree, Books, etc, And Non-count…
Q: It takes an operator 2 min to service a machine and 0.5 min to walk to the next machine. Each…
A:
Q: 1. A certain batch of parts is routed through six machines in a batch production plant. The setup…
A: Hello. Since you have posted multiple questions and not specified which question needs to be solved,…
Q: The following four jobs must be processed through a three-machine flow shop.MachineJob A B C1 4 262…
A: Here, Minimum time taken in machine C>Maximum time taken in machine B Hence we turn the problem…
Q: A fast moving item has a demand of 18000 units/year. The cost of one procurement is Rs. 50 and…
A:
Q: The annual demand for an item is 10,000 units. The unit cost is Rs. 100 and inventory carrying…
A: Given data: The annual demand for an item is D = 10000 units. The unit cost is Cu = 100 Rs. The…
Q: A manufacturing company is planning the process for meeting a customer's order for a particular…
A:
Q: The table below lists the time estimates and immediate predecessor(s) for each activity in a product…
A: Given Data
Q: Suppose that four machines, 1, 2, 3, and 4 have been identified as belonging in a Group Technology…
A:
Q: The annual demand for an item is 10,000 units. The unit cost is Rs. 100 and inventory carrying…
A: Given:Demand, D=10000 unitsordering cost, Co=Rs 2000 holding cost, Ch=14.4 %
Q: Answer the following problems in Job Sequencing
A: Consider the table shown below. S. No. Machine A Machine B 1 8 7 2 10 15 3 11 10 4 12 14…
Q: A collection of operations and processes used to obtain a desired product is called a; Manufacturing…
A: Production system: A system in an industry that use any method to produce goods and services form…
Q: Q#05 (a) :The Lift Mechanism for the package moving is desired to raise (your registration number)…
A:
Q: The demand of a certain part is 1000 parts/year and its cost is 71000/part. The orders are placed…
A: Given, Demand of the part = D = 1000 parts/year Cost of the part = C = Rs. 1000/part Cost of…
Q: The processing times for five jobs and their due dates are given for a single machine scheduling…
A: Given : Use the shortest processing time(SPT) Job(j) Processing Time(t) in hours Due date(d) in…
Q: Table 1 shows a direct time study data from an assembly line. Job element B is in automatic mode…
A: We have given
Q: Four machines used to produce a family of parts are to be arranged into a GT cell. The from-to data…
A: (a) Write the Hollier's algorithm to construct the layout, FROM/TO 1 2 3 4 FROM Sum FROM/TO ratio…
Q: 3. The manufacturer has got a demand of an item of 3600 units/ year. inventory carrying charges is…
A: Given data: The number of demand of an item is D=3600 unitsyear The inventory carrying cost is…
Q: Automated industrial system can increase the quality and flexibility of process. (i) Sketch an…
A: An automated industrial system
Q: For Each of the following activities, determine the maximum delay in the starting time relative to…
A: The total float is the duration a project can delay without delay the project time. The free float…
Q: A certain job shop specializes in one-of-a-kind orders dealing with parts of medium-to-high…
A: Given data as per question
Q: A batch of 35 parts is ordered by a customer about every six months. The parts are currently…
A: Step 1: Given Data No of parts = 35Delay time = 10/hr per machineSet up time = 2hrMachine…
Q: Describe the similarities and differences between calculadng an average rate of change and an…
A: The average rate at which one quantity changes in relation to something else changing is…
Q: Suppose that four machines, 1, 2, 3, and 4 have been identified as belonging in a Group Technology…
A: Group Technology is basically applicable in production flow analysis It is an easy to use an…
Q: Lehen Vinters imports a certain brand of beer. The demand, which may be assumed to be uniform, is…
A:
Q: The word "option" refers to the fact that you have the ability to alter the way the FMS functions.
A: Flexible manufacturing system (FMS) is a creation technique that is intended to effectively adjust…
Q: In a single machine scheduling problem, all the jobs will have different sequences. true or false
A: In a single machine scheduling problem, different jobs are processed over a single machine. Since we…
Q: There are five jobs (namely 1,2,3,4 and 5), each of which must go through machines A, B and C in the…
A: To determine the sequence of job operations.
Q: Monthly delivery rate for a part supplied to an automotive assembly plant is 12,500 pc. There are 20…
A: Given : Number of parts = 12500 Number of working days in February = 20 Number of working days in…
Q: In a job shop scheduling problem, all the jobs will have the same sequences.
A: In a job shop scheduling problem, all the jobs will have the same sequences. Answer: True
Q: There are 5 jobs that need to be sequenced in a work center. What will be the average flow time if…
A:
Q: A machine makes two components; call them types A and B. It takes 250 seconds to switch production…
A: The average inventory of B can be given as,
Q: AutoCAD is one of the ready-made that help workers in the field of design and engineering drawing…
A: in AUTO CAD we draw and edit the 2D or 3D modelings
Q: The objective of the assignment problem is to assign the jobs, then the assignment cost will be. O…
A: The objective of the assignment is to assign the jobs, then the assignment cost will be minimum…
Q: Six jobs arrived in a sequence as given below: Jobs Processing Time (in Days) I 4 II III IV 10 V VI…
A: For the given case, Processing time required for each job is as below. TI = 4 days TII = 9 days TIII…
Q: 4) A factory manufactures chairs, tables and bookcases each requiring the use of three operations:…
A: Write the objective function and constraints. Objective…
Q: Table 3 shows the process sequence in a production line and its related direct time study data. The…
A: Given: During a time study of processing of a product, it is found that operations performed in…
Q: A flow-line mass production operation consists of six manual workstations. Work units are moved…
A: (a) Given: No. of workstations = 6 Transfer time of each station = 10 sec Cycle Time: The cycle time…
Q: In a factory, the direct cost is also called variable cost because: It is connected with the…
A:
Q: A machine operator has to perform 3 operations, Turning, Threading & Knurling on three machines A, B…
A:
Q: produce washing and dryer machines Ditteret are manufactured by press and ferts for each product The…
A: As per honor code and answering guidelines I can answer 1st question at a time.If you want other…
i need the answer quickly
Step by step
Solved in 2 steps with 2 images
- = Consider a four aisle AS/RS in which an S/R machine is used for each aisle. The length of the storage aisle 85 m and its height = 14 m. Suppose horizontal and vertical speeds of the S/R machine are 61 m/min and 23 m/min, respectively. The S/R machine requires 20 s to accomplish a P&D operation. The aisles in the AS/RS will be organized to follow a class-based dedicated storage strategy. There will be two classes, according to activity level. The more active stock is stored in the half of the rack system that is located closest to the input/output station, and the less active stock is stored in the other half of the rack system farther away from the input/output station. Within each half of the rack system, random storage is used. The more active stock accounts for 80% of the transactions, and the less active stock accounts for the remaining 20%. Assume that system utilization = 90%, and the number of single-command cycles = the number of dual-command cycles. Determine the throughput…The processing times for five jobs and their due dates are given for a single machine scheduling below. Using the Shortest Processing Time (SPT):- Job (j) 1 2 3 4 5 Processing time (t) in hours 9 7 5 11 6 Due date (d) in days 16 20 25 15 40 (a) Determine the sequence (b) Total completion time (c) Average completion time (d) Average number of jobs in the system (e) Average job latenessThe three-station work cell at Pullman Mfg., Inc. is illustrated in the figure below. It has two machines at station 1 in parallel (i.e., the product needs to go through only one of the two machines before proceeding to station 2). 30 min/unit Station 1 Machine A Station 2 Station 3 Station 1 3 min/unit 2 min/unit Machine B 30 min/unit a) The throughput time is minutes (enter your response as a whole number). b) The bottleneck time of this work cell is minutes per unit (enter your response as a whole number). c) is the bottleneck station d) If the firm operates 8 hours per day, 6 days per week, the weekly capacity of this work cell is units (enter your response as a whole number).
- Three machines are used in a group-technology cell to process a family of five parts. Thetable below lists production quantities (Qj), production times (Tpij), and machine fractionsfor each family member (fij). Part E requires a changeover time of 5 min on each machine soit is produced in batches of 5 parts. Nonoperation times (Tno) are the same for all parts andmachines: 25 min per machine. Determine (a) average hourly production rate for the cell,(b) utilization of each machine and average utilization of the cell, (c) manufacturing leadtime, and (d) work-in-process. A spreadsheet calculator is recommended for this problemUsing signavio or any PBM tools and must Use pool and lane and object. Model the following business process at a supplier. After a supplier notifies a retailer of the approval of a purchase order, the supplier can receive an order confirmation, an order change, or an order cancelation from the retailer. It may happen that no response is received at all. If no response is received after 48 h, or if an order cancelation is received, the supplier will cancel the order. If an order confirmation is received within 48 h, the supplier will process the order normally. If an order change is received within 48 h, the supplier will update the order and ask again the retailer for confirmation. The retailer is allowed to change an order at most three times. Afterwards, the supplier will automatically cancel the order.The gross requirements for item Z are specified for the beginning of weeks 1 through 8 in the table that follows. Gross Requirements for Item Z 1 2 3 6 7 8 Week 4 Gross Requirement 180 90 180 0 360 0 90 90 The lead time is 2 weeks. The current on hand inventory, at the beginning of week 1 is 360 units. If the order cost is $540 per order and the inventory cost is $3 per unit per period, and the order quantity is the computed part period (or a multiple of the computed part period) when it is necessary to place an order, what is the total cost for the 8 week period? Report as a whole number with no commas. Answer: The correct answer is: 4590
- Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise. Time to Complete Task (seconds): Task 1: 30 Task 2: 25 Task 3: 15 Task 4: 20 Task 5: 15 Task 6: 20 Task 7: 50 Task 8: 15 Task 9: 20 Task 10: 25 Task 11: 15 Task 12: 20 The current conveyor-paced assembly-line configuration assigns the workers in the following way: • Worker 1: Tasks 1, 2, 3 • Worker 2: Tasks 4, 5, 6 • Worker 3: Tasks 7, 8, 9 • Worker 4: Tasks 10, 11, 12 What is the capacity of the current line (in units per hour)?8086 Microprocessor lab. | 9 Discussion: Two word - wide unsigned integers are stored at the memory addresses OA00 H and OA02 H respectively, Write an instruction sequence that computes and stores their sum, difference, product, and quotient then Store these results at consecutive memory locations starting at address 0A10 H in memory. To obtain the difference, subtract the integer at OA02 H from the integer at OA00 H. For the division, divide the integer at OA00H by the integer at OA02 H. Use register indirect relative addressing mode to store the various result.The main reason to do Design for Manufacturing (DFM) is? O a. To predict costs O b. To improve the design of the products Oc To predict time O d. To estimate cost evaluation for further system analysis:
- desired output rate is 75 units I have a pnocess ar follons: have a y: process ar follows Task Time (seconds) Predecessor None 45 A 30 None A,B 45 B 20 10 17 D,E 40 my desired output rate is 75 units hour, what is per the efficiency of y setup? Aniwer to 20eemals. my you nd the c tall in ow value you eted Val ween Id be zer no differ sauare St eused for statistical v ed to Conve hore alrelaConsider the following instance of the two-machine job shop with the makespan as objective (J2 || Cmax). Job 2 3 6. 7. 8 1. 4 P1j 12 3 4 10 3 P2j 3 8 7 3 6. 11 Route Mi-> M1-> M2-> M1-> M2-> M2-> M1 M2 M2 М2 M1 M2 M1 M1 1. Apply the shifting bottleneck heuristic to this two-machine job shop. 2. Apply the SPT(1)-LPT(2) heuristic to this two-machine job shop. 3. Compare the schedules found under (1), (2). 2.Explain Following in detail. Please give Handwritten answer 1.Vector Managed Inventory 2.ABC Inventory 3.Method Time Management 4.Predetermined Motion Time System