Project A Project B Project C Project D Based on the data obtained from each project, you have found out the value of work done on the 31st of March, which is shown in Table 2 below. Project Table 1: The Planned Value of Work Done Schedule Feb March Jan 60,000 100,000 120,000 100,000 80,000 120,000 80,000 80,000 70,000 120,000 120,000 100,000 Table 2: The Actual Value of Work Done and Direct Cost Incurred as of the 31st of March ABCD с April May 120,000 200,000 140,000 140,000 90,000 100,000 120,000 150,000 Actual Value of Work Done 300,000 250,000 250,000 280,000 Direct Cost Incurred 220,000 180,000 200,000 240,000 Each project is supposed to contribute 10% profit and 8% overhead to the company. You are requested to present to the company the turnover as of the 31st of March. Prepare your answer by answering. the following questions. a) Calculate the planned value of work. done, the total planned overhead and the total profit contribution from all the projects as of the 31st of March. b) Calculate the actual value of work done. and the total actual profit contribution from all the projects as of the 31st of March. c) Analyse planned and actual nett profit contribution of all the projects as of the 31st of March, and comment on the status of the projects. on the variance between the
Project A Project B Project C Project D Based on the data obtained from each project, you have found out the value of work done on the 31st of March, which is shown in Table 2 below. Project Table 1: The Planned Value of Work Done Schedule Feb March Jan 60,000 100,000 120,000 100,000 80,000 120,000 80,000 80,000 70,000 120,000 120,000 100,000 Table 2: The Actual Value of Work Done and Direct Cost Incurred as of the 31st of March ABCD с April May 120,000 200,000 140,000 140,000 90,000 100,000 120,000 150,000 Actual Value of Work Done 300,000 250,000 250,000 280,000 Direct Cost Incurred 220,000 180,000 200,000 240,000 Each project is supposed to contribute 10% profit and 8% overhead to the company. You are requested to present to the company the turnover as of the 31st of March. Prepare your answer by answering. the following questions. a) Calculate the planned value of work. done, the total planned overhead and the total profit contribution from all the projects as of the 31st of March. b) Calculate the actual value of work done. and the total actual profit contribution from all the projects as of the 31st of March. c) Analyse planned and actual nett profit contribution of all the projects as of the 31st of March, and comment on the status of the projects. on the variance between the
Accounting Information Systems
11th Edition
ISBN:9781337552127
Author:Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Publisher:Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Chapter11: The Billing/accounts Receivable/cash
receipts (b/ar/cr) Process
Section: Chapter Questions
Problem 9P: Use the DFDs in Figure 11.3 (pg. 416), Figure 11.4 (pg. 417), Figure 11.6 (pg. 419), and Figure 11.8...
Related questions
Question
![Table 1: The Planned Value of Work Done Schedule
Jan
Feb
March
Project A
Project B
Project C
Project D
60,000
100,000
80,000
120,000
100,000
80,000
80,000
120,000
120,000
120,000
70,000
100,000
April
120,000
140,000
90,000
120,000
Мay
200,000
140,000
100,000
150,000
Based on the data obtained from each project, you have found out the value of
work done on the 31st of March, which is shown in Table 2 below.
Table 2: The Actual Value of Work Done and Direct Cost Incurred as of the
31st of March
Project
Actual Value of Work
Done
300,000
250,000
250,000
280,000
Direct Cost Incurred
A
220,000
180,000
200,000
240,000
Each project is supposed to contribute 10%
profit and 8% orerhead to the compoany.
You are requested to present to the
company the turnorer as of the 31st of
march. Prepare your answenr by answering
the following que'stions.
a) Calculate the planned ralue of work
done, the total planned orerhead and the
total profit contribution from all the.
projects as of the 31st of March.
b) Calculate the actual ralue of work done
and the totalactual profit contribution
from all the projects as of the 31st of
march.
c) Analyse
planned and actual nett profit
contribution of all the projects as of the
31stof march, and comment on the status
of the projects.
on the rariance between the](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Ff6eb33f4-142b-486d-8f81-ce3df2c70098%2F867bd2f7-efd0-45a6-ae76-b8a04ac615e3%2Fi2shfwz_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Table 1: The Planned Value of Work Done Schedule
Jan
Feb
March
Project A
Project B
Project C
Project D
60,000
100,000
80,000
120,000
100,000
80,000
80,000
120,000
120,000
120,000
70,000
100,000
April
120,000
140,000
90,000
120,000
Мay
200,000
140,000
100,000
150,000
Based on the data obtained from each project, you have found out the value of
work done on the 31st of March, which is shown in Table 2 below.
Table 2: The Actual Value of Work Done and Direct Cost Incurred as of the
31st of March
Project
Actual Value of Work
Done
300,000
250,000
250,000
280,000
Direct Cost Incurred
A
220,000
180,000
200,000
240,000
Each project is supposed to contribute 10%
profit and 8% orerhead to the compoany.
You are requested to present to the
company the turnorer as of the 31st of
march. Prepare your answenr by answering
the following que'stions.
a) Calculate the planned ralue of work
done, the total planned orerhead and the
total profit contribution from all the.
projects as of the 31st of March.
b) Calculate the actual ralue of work done
and the totalactual profit contribution
from all the projects as of the 31st of
march.
c) Analyse
planned and actual nett profit
contribution of all the projects as of the
31stof march, and comment on the status
of the projects.
on the rariance between the
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 5 steps with 6 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337552127/9781337552127_smallCoverImage.gif)
Accounting Information Systems
Finance
ISBN:
9781337552127
Author:
Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Publisher:
Cengage Learning
![Pkg Acc Infor Systems MS VISIO CD](https://www.bartleby.com/isbn_cover_images/9781133935940/9781133935940_smallCoverImage.gif)
Pkg Acc Infor Systems MS VISIO CD
Finance
ISBN:
9781133935940
Author:
Ulric J. Gelinas
Publisher:
CENGAGE L
![Survey of Accounting (Accounting I)](https://www.bartleby.com/isbn_cover_images/9781305961883/9781305961883_smallCoverImage.gif)
Survey of Accounting (Accounting I)
Accounting
ISBN:
9781305961883
Author:
Carl Warren
Publisher:
Cengage Learning
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337552127/9781337552127_smallCoverImage.gif)
Accounting Information Systems
Finance
ISBN:
9781337552127
Author:
Ulric J. Gelinas, Richard B. Dull, Patrick Wheeler, Mary Callahan Hill
Publisher:
Cengage Learning
![Pkg Acc Infor Systems MS VISIO CD](https://www.bartleby.com/isbn_cover_images/9781133935940/9781133935940_smallCoverImage.gif)
Pkg Acc Infor Systems MS VISIO CD
Finance
ISBN:
9781133935940
Author:
Ulric J. Gelinas
Publisher:
CENGAGE L
![Survey of Accounting (Accounting I)](https://www.bartleby.com/isbn_cover_images/9781305961883/9781305961883_smallCoverImage.gif)
Survey of Accounting (Accounting I)
Accounting
ISBN:
9781305961883
Author:
Carl Warren
Publisher:
Cengage Learning
![Intermediate Financial Management (MindTap Course…](https://www.bartleby.com/isbn_cover_images/9781337395083/9781337395083_smallCoverImage.gif)
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
![Financial Management: Theory & Practice](https://www.bartleby.com/isbn_cover_images/9781337909730/9781337909730_smallCoverImage.gif)