In 20x1, ABC Co. was contracted to build a railroad. The contract price is equal to the construction costs incurred plus 20% thereof. However, if the project is completed within 4 years, ABC will receive an additional payment of P200,000. Information on the project is shown below: 20x1 20x2 Costs incurred to date Estimated costs to complete 2,400,000 3,600,000 4,575,000 1,525,000 20x3 6,125,000 125,000 In 20x1 and 20x2, it was not highly probable that the project will be completed on time. However, in 20x3, ABC assessed that the project will be completed earlier than originally expected and thus it is now highly probable that the incentive payment will be received.

CONCEPTS IN FED.TAX.,2020-W/ACCESS
20th Edition
ISBN:9780357110362
Author:Murphy
Publisher:Murphy
Chapter3: Income Sources
Section: Chapter Questions
Problem 88P
icon
Related questions
Question
Questions: 1. How much revenue is recognized in the contract in 20x3? 2. How much profit is recognized in the contract in 20x3?
In 20x1, ABC Co. was contracted to build a railroad. The contract price is equal to the construction
costs incurred plus 20% thereof. However, if the project is completed within 4 years, ABC will receive
an additional payment of P200,000. Information on the project is shown below:
20x1
20x2
Costs incurred to date
Estimated costs to complete
2,400,000
3,600,000
4,575,000
1,525,000
20x3
6,125,000
125,000
In 20x1 and 20x2, it was not highly probable that the project will be completed on time. However, in
20x3, ABC assessed that the project will be completed earlier than originally expected and thus it is
now highly probable that the incentive payment will be received.
Transcribed Image Text:In 20x1, ABC Co. was contracted to build a railroad. The contract price is equal to the construction costs incurred plus 20% thereof. However, if the project is completed within 4 years, ABC will receive an additional payment of P200,000. Information on the project is shown below: 20x1 20x2 Costs incurred to date Estimated costs to complete 2,400,000 3,600,000 4,575,000 1,525,000 20x3 6,125,000 125,000 In 20x1 and 20x2, it was not highly probable that the project will be completed on time. However, in 20x3, ABC assessed that the project will be completed earlier than originally expected and thus it is now highly probable that the incentive payment will be received.
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L