Bulluck Corporation makes a product with the following standard costs:     Standard Quantity or Hours Standard Price or Rate Direct materials 3.5 grams $ 1.00 per gram Direct labor 0.7 hours $ 11.00 per hour Variable overhead 0.7 hours $ 2.00 per hour   The company reported the following results concerning this product in July.   Actual output 3,000 units Raw materials used in production 11,370 grams Actual direct labor-hours 1,910 hours Purchases of raw materials 12,100 grams Actual price of raw materials purchased $ 1.20 per gram Actual direct labor rate $ 11.40 per hour Actual variable overhead rate $ 2.10 per hour   The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased.   The materials price variance for July is:   Multiple Choice   A. $2,100 U   B. $2,420 F   C. $2,100 F   D. $2,420 U

Managerial Accounting: The Cornerstone of Business Decision-Making
7th Edition
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Chapter10: Standard Costing And Variance Analysis
Section: Chapter Questions
Problem 72P: Moleno Company produces a single product and uses a standard cost system. The normal production...
icon
Related questions
Topic Video
Question

 

Bulluck Corporation makes a product with the following standard costs:

 

  Standard Quantity or Hours Standard Price or Rate
Direct materials 3.5 grams $ 1.00 per gram
Direct labor 0.7 hours $ 11.00 per hour
Variable overhead 0.7 hours $ 2.00 per hour

 

The company reported the following results concerning this product in July.

 

Actual output 3,000 units
Raw materials used in production 11,370 grams
Actual direct labor-hours 1,910 hours
Purchases of raw materials 12,100 grams
Actual price of raw materials purchased $ 1.20 per gram
Actual direct labor rate $ 11.40 per hour
Actual variable overhead rate $ 2.10 per hour

 

The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased.

 

The materials price variance for July is:

 

Multiple Choice
 
A. $2,100 U
 
B. $2,420 F
 
C. $2,100 F
 
D. $2,420 U
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub