(b) Develop an activity schedule. (Round your answers to two decimal places.) Latest Start Activity A B с D E F G H I 0 1.17 1.17 7.17 7.17 1.17 9.17 11.17 13.17 Earliest Start ✓ 0 1.17 3.17 7.17 10.17 11.17 9.17 11.17 13.17 ✓ ✓ 1.17 7.17 5.17 9.17 10.17 3.17 11.17 13.17 14.17 Earliest Finish (c) What are the critical activities? (Enter your answers as a comma-separated list.) 1.17 7.17 7.17 9.17 13.17 13.17 11.17 13.17 14.17 Latest Finish ✓ lo 0 2 0 3 10 0 0 0 Slack > > > ✓
Q: Consumer-oriented tablets are radically altering how organizations store, retrieve, and use…
A: Data visualization tools, such as KPI monitoring, are essential for efficient and effective…
Q: Explain the basic compensation objectives of pay systems. Compensation systems can be tailored to…
A: NOTE: We are allowed to do the first three sub-parts only. Strategic management is the process of…
Q: Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40…
A: Precedence diagram:
Q: How should I approach note-taking in my CS course
A: Taking effective notes is an important aspect of learning in any academic course, and this is…
Q: Consider a birth-and-death process with just three attainable states (0, 1, and 2), for which the…
A: NOTE: We are allowed to do the first three sub-parts only. Let the states be denoted by n = 0, 1, 2…
Q: A copy machine is available 24 hours a day. On a typical day, the machine produces 113 Jobs. Each…
A: Overall Equipment Effectiveness The OEE of a manufacturing process is calculated by comparing actual…
Q: Choose two companies and provide a reaction paper comparing the two different companies as to how…
A: Below is the comparison of two different companies on their training methods:
Q: What does "software as a service" really mean
A: Providing applications via Web-like services is known as software as a service. SaaS applications…
Q: Is there a strategy in place to safeguard a strategy's most vital components?
A: Strategic management involves setting goals and objectives, analyzing the competitive environment,…
Q: How can trends and patterns be identified to help with market forecasting
A: With the help of trends, we could show a general direction of marketing forecasted data or demand…
Q: Excel has over 60 different types of charts. Select any 2 (two) and compare and contrast their…
A: A chart is unique in relation to a graph. It tends to be addressed in many structures and isn't…
Q: A service blueprint is best defined as: a process flowchart a process flow chart…
A: A service blueprint is best characterized as an outline that pictures connections between…
Q: Craft a high-level Procurement Management Plan for the project. Craft a high-level Human Resource…
A: A procurement management plan is a written document that defines the methods and tactics for…
Q: There are three factors that must be considered while crafting a security plan.
A: The three factors that considered while crafting security plan are Confidentiality: Confidentiality…
Q: Forecasting Room Congratulations, the design options for the two mobile phone lines have been…
A: Demand forecasting is the method involved with anticipating future demand for an item or…
Q: Name and describe the different ways that learning occurs in a company.
A: Employees need regular learning to ensure they are using the most up-to-date tools and methods in…
Q: Describe how THE PROCESS DIAGRAM BELOW they could be improved and make recommendations for their…
A: Operational customer service managers assume a basic part in guaranteeing that businesses give…
Q: Kindly prepare five (5) SMART objectives for the post of Court Administrator - Administratively,…
A: SMART objectives are objectives that are Specific, Measurable, Achievable, Relevant, and Time-bound.…
Q: Can you see any common blunders made in Performance Testing?
A: Note : "The answer has been framed in a generalized manner." Project management is the process in…
Q: Johnson Cogs wants to set up a line to serve 100 customers per hour. The work elements and their…
A: The theoretical minimum number of workstations alludes to the minimum number of workstations…
Q: Need assistance in the procurement plan question based on the senario FAO-Funded Aquaponics…
A: A Procurement Management Plan can be defined as the formal record that frames the processes and…
Q: 1. What direct materials are used in the production of gummy bears? 2. What direct labor costs are…
A: The case discusses Haribo, a global confectionery company that has been producing gummy bears for…
Q: Draw a c- chart
A: Here, for each week, I have been given the number of complaints, for this dataset, I would construct…
Q: a) Show the feasible region. (b) What are the extreme points of the feasible region? (b) What are…
A: Linear programming is a mathematical optimization technique used to find the best solution to a…
Q: Which of the following represent(s) strategic challenges of competing in a new industry? O A firm…
A: Strategic management is the process of planning, implementing, and evaluating an organization's…
Q: 1. Study the supply chain integration of companies operating in Namibia below and identify the TYPE…
A: A crucial component of supply chain management, supply chain integration entails coordination and…
Q: Explain IT project management tools and technologies.
A: IT project management tools and technologies are essential for project managers for making plan,…
Q: A student wrote Answer. Level: Strategic Management in Retail Strategic managers are key players…
A: Strategic management is essential for the survival and success of retail companies in a highly…
Q: Question 17 How is usually corporate efficiency achieved · A proper partition and distribution…
A: Answer 17: Corporate efficiency can be achieved through a various of methods and approaches. Some…
Q: A unit has a constant failure rate of 0.3% per 1000 hours. What is its MTBF? What are the…
A: MTBF stands for Mean Time Between Failures. It is a measure of the expected time between two…
Q: Discuss the strategic needs and challenges that transportation managers face. How can third-party…
A: SUMMARY- Transportation management includes the powerful preparation and management of logistics…
Q: These four elements make up what is often known as a machine cycle or process loop. Which parts of a…
A: The four components of a machine cycle or process loop input, processing, output, and storage, are…
Q: Develop a work breakdown structure (WBS) for an aquaponic training workshop for 40 people, in text…
A: A closed-loop system that combines the growth of fish and plants is known as aquaponics. Yet, the…
Q: It is possible to summarize the five phases of the system development life cycle as follows. Just…
A: The System Development Life Cycle (SDLC) is a process used in software development to plan, design,…
Q: Provide a brief (5-sentence) explanation of Lean Development and its advantages, and then give two…
A: Lean Development is a methodology for software development that underscores limiting waste and…
Q: 1. Introduction: Provide general information on the company (what it does, where it operates, who…
A: For the above-given question, we are using Tesla as a company. Tesla is a spearheading organization…
Q: Re-order level (ii) Optimum order quantity and total inventory costs (iii) Maximum stock level
A: NOTE: We are allowed to do the first three sub-parts only. Given: Order cost (S) = K100 Raw…
Q: Hatch Financial, which recently absorbed another firm, is now downsizing and must relocate five…
A: Find the Given details below: Given details: Analyst Moving cost to Gary Salt lake city…
Q: What is the best approach to evaluating an ERP system, regardless of the type?
A: Enterprise resource planning systems centralize data from across an organization into a unified…
Q: The following table shows the actual demand observed over the last 11 years: Year Demand 1 8 2 10 3…
A: Firstly solving (B): Using the Three year moving Average forecast from Periods 4 -12 are: Period 4 =…
Q: These actions were considered to be important if they were to reduce the overall cost and stay ahead…
A: CASE SUMMARY- Juan Hernandez, the head buyer of Connery Manufacturing Company, was elevated to the…
Q: Priority Scheduling resembles Shortest Job First Scheduling in what ways?
A: Priority Scheduling and Shortest Job First (SJF) Scheduling is both CPU scheduling algorithms used…
Q: It is evident that organizations must take advantage of opportunities, but in the context of a 20…
A: The 20-Mile March is one of the book's most interesting ideas. It expresses the notion that the most…
Q: What are the main processes in system installation and evaluation
A: Installing, testing, and assessing new systems inside an organization are crucial operations…
Q: a. Determine the S UCL and LCL for a c-chart with 2-2. (Leave no cells blank. Round up any negative…
A: Here, each sample has the data of irregularities, I would determine the C bar value, Sc, UCL, and…
Q: Unions have played a significant role during the history of our organizations. Question 1: Why were…
A: ANSWER 1 : Unions were primarily organized to protect rights and interests of workers, especially…
Q: Blair & Rosen, Inc. (B&R), is a brokerage firm that specializes in investment portfolios designed to…
A: Decision Variables: Suppose-N = Internet fund investment in thousandsB = Blue chip fund investment…
Q: You may need to use the appropriate technology to answer this question. A health and nutrition store…
A: Information Given Annual demand (D) = 1000 units Cost of ordering (Co) = 26.50 Cost of holding (Ch)…
Q: What is the project duration?
A: Here, each activity has the immediate predecessor data and the time estimates, I would determine the…
Q: Complete the chase production plan, using the following information. The only costs you need to…
A: Given- Hiring Cost= $4,000 per workerFiring Cost = $3,000 per workerInventory Holding Cost = $9 per…
Step by step
Solved in 2 steps with 4 images
- Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. A project network with 11 activities and 13 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity F. Activity B…Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. (b) Develop an activity schedule. (Round your answers to two decimal places.) (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project…Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. (b) Develop an activity schedule. (Round your answers to two decimal places.) (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project…
- You are in charge of a project at the local community center. The center needs to remodel one ofthe rooms in time for the start of a new program. Delays in the project mean that the center mustrent other space at a nearby church at additional cost. Time and cost data for your project arecontained in below table. Your interest is in minimizing the cost of the project to the communitycenter.Using the normal times for each activity, what is the earliest date you can complete the project?Suppose the variable overhead costs are $50 per day for your project. Also, suppose that thecenter must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-costproject schedule using below format.The AON diagram for the community center project is below. Crash 4 times and find total cost.Farihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.You may need to use the appropriate technology to answer this question. Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. A project network with 11 activities and 13 directed arcs is shown. Activity Start is connected to activity A. Activity A…
- Only typed explanation The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 14. What is the shortest time duration for this project regardless of cost? What is the minimum total cost associated with completing the project in 14 weeks? What is the total time of the minimum-cost schedule?For this assignment, you will design a risk management plan for a project titled “prolonged waiting times for patients in a large outpatient hospital” that will include the following elements: Risk Register/Matrix (list of at least 5 (five) risks along with the associated impact and probability scores along with risk score) Contingency plan (list of any risks you will plan for in advance along with what triggers the contingency). Be sure to include any information useful to stakeholders on the rationale for the creation of these elements as well as any outside references supporting the risk management plan.You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in the table. Your interest is in minimizing the cost of the project to the community center. a. Using the normal times for each activity, what is the earliest date you can complete the project? b. Suppose the variable overhead costs are $50 per day for your project. Also, suppose that the center must pay$40 per day for a temporary room on day 15 or beyond. Find the minimum-cost project schedule.
- Describe the various purposes of using project scheduling?Which activities are noncritical or can be delayed? (You must also complete the table below) Note: to means optimistic time , tm means most likely time , tp pessimistic time, and te means expected activity time estimate.IS Development Assignment Notes Assume that you are in charge of IS for a mid-sized oil and natural gas company. The CEO is interested in developing an application that will give him information about the amount of natural gas passing through pumping stations located around North America. He wants it to work on his desktop, iPad, and smartphone. The features he wants on the application change every time you speak with him and you’re still in the planning phase. Now he’s asked for a schedule. How do you respond?