Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs assigned to this job? Direct materials Direct labor Manufacturing overhead Source Documents (2) Overhead is applied on the basis of direct labor cost. What is the predetermined manufacturing overhead rate? Predetermined manufacturing overhead rate (3) What are the total cost and the unit cost of the completed job? (Round unit cost to 2 decimal places, e.g. 1.25.) Total cost of the completed job $ Unit cost of the completed job % $

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter4: Job Order Costing
Section: Chapter Questions
Problem 15EB: A companys individual job sheets show these costs: Overhead is applied at 1.75 times the direct...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Answer the following questions.
(1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs assigned to this job?
Direct materials
Direct labor
Manufacturing overhead
Source Documents
(2) Overhead is applied on the basis of direct labor cost. What is the predetermined manufacturing overhead rate?
Predetermined manufacturing overhead rate
(3) What are the total cost and the unit cost of the completed job? (Round unit cost to 2 decimal places, e.g. 1.25.)
Total cost of the completed job $
Unit cost of the completed job
%
$
Transcribed Image Text:Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs assigned to this job? Direct materials Direct labor Manufacturing overhead Source Documents (2) Overhead is applied on the basis of direct labor cost. What is the predetermined manufacturing overhead rate? Predetermined manufacturing overhead rate (3) What are the total cost and the unit cost of the completed job? (Round unit cost to 2 decimal places, e.g. 1.25.) Total cost of the completed job $ Unit cost of the completed job % $
A job cost sheet of Sunland Company is given below.
JOB NO.
ITEM
FOR
Date
7/10
12
15
22
24
27
31
469
Total cost
Unit cost
White Lion Cages
Todd Company
Direct
Materials
700
900
Cost of completed job:
Direct materials
Direct labor
1,675
1,525
Manufacturing overhead
Job Cost Sheet
Quantity
Date Requested
Date Completed
Direct
Labor
500
300
700
2,500
7/2
7/31
Manufacturing
Overhead
625
375
875
Transcribed Image Text:A job cost sheet of Sunland Company is given below. JOB NO. ITEM FOR Date 7/10 12 15 22 24 27 31 469 Total cost Unit cost White Lion Cages Todd Company Direct Materials 700 900 Cost of completed job: Direct materials Direct labor 1,675 1,525 Manufacturing overhead Job Cost Sheet Quantity Date Requested Date Completed Direct Labor 500 300 700 2,500 7/2 7/31 Manufacturing Overhead 625 375 875
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College