An automobile manufacturer wants to award contracts for the supply of four different fuel injection system components. Four contracts have submitted bids on the components; the Table below summarizes the prices bid per unit. Where no entry is made, the contractor submitted no bid.   Component Contractor 1 2 3 4 1 $25 - $30 $40 2 $28 $80 $28 - 3 - $75 $33 - 4 $30 $82 - $42 Demand (units) 15,000 30,000 10,000 20,000 The demand for a component does not have to be supplied completely by one contractor. In fact, certain contractors have indicated maximum quantities that can be supplied at the bid price. Contractor 1 can supply no more than 18,000 of item 4, contractor 2 no more than 3,000 of item 1, contractor 4 no more than 15,000 units of item 2 and no more than 5,000 of item 4. There is no provision that awards must go to the low bidder. The automobile manufacturer wants to determine how many units of each item should be awarded to each contractor so as to minimize total costs for the four items. Contractor 4 has specified that it requires a minimum award of $500,000 if it is to supply any items at all. The automobile manufacturer wishes to avoid awarding over $1.2 million in awards to any one company. Formulate the LP model that can solve this problem. Would you say that divisibility is a practical problem here? Explain. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter9: Decision Making Under Uncertainty
Section: Chapter Questions
Problem 30P
icon
Related questions
Question
  1. An automobile manufacturer wants to award contracts for the supply of four different fuel injection system components. Four contracts have submitted bids on the components; the Table below summarizes the prices bid per unit. Where no entry is made, the contractor submitted no bid.
 

Component

Contractor

1

2

3

4

1

$25

-

$30

$40

2

$28

$80

$28

-

3

-

$75

$33

-

4

$30

$82

-

$42

Demand (units)

15,000

30,000

10,000

20,000

The demand for a component does not have to be supplied completely by one contractor. In fact, certain contractors have indicated maximum quantities that can be supplied at the bid price. Contractor 1 can supply no more than 18,000 of item 4, contractor 2 no more than 3,000 of item 1, contractor 4 no more than 15,000 units of item 2 and no more than 5,000 of item 4.

There is no provision that awards must go to the low bidder. The automobile manufacturer wants to determine how many units of each item should be awarded to each contractor so as to minimize total costs for the four items. Contractor 4 has specified that it requires a minimum award of $500,000 if it is to supply any items at all. The automobile manufacturer wishes to avoid awarding over $1.2 million in awards to any one company.

Formulate the LP model that can solve this problem. Would you say that divisibility is a practical problem here? Explain.

Note:-

  • Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism.
  • Answer completely.

You will get up vote for sure.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Knowledge Booster
Business reports
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning