A completed project consisted of the following activities, many of which were delayed: Activity Predecessor Duration Delay Party at fault A 8 8 Neutral B C UO D E F G . A B B D A F 6 3 3 7 9 10 4 25 12 1 2 Owner Neutral Contractor Owner Owner The delays in the table above affected the start of each activity. Once each activity started, it took exactly the planned time in the table above for that activity to finish. The time for practical completion for the project originally set in the contract was 29 days. Calculate the total extension of time that should be granted to the contractor for all applicable delays using the following methods: The impacted as-planned method: [ The collapsed as-built method: The time impact method:

Linear Algebra: A Modern Introduction
4th Edition
ISBN:9781285463247
Author:David Poole
Publisher:David Poole
Chapter2: Systems Of Linear Equations
Section2.4: Applications
Problem 28EQ
icon
Related questions
Question
A completed project consisted of the following activities, many of which were delayed:
Activity Predecessor Duration Delay Party at fauit
A
8.
Neutral
B
A
6.
3
4.
Owner
Neutral
B.
3.
25
E
D
12 Contractor
A
6.
Owner
F
10
2
Owner
The delays in the table above affected the start of each activity. Once each activity started, it took exactly the planned time in the table above for that
activity to finish.
The time for practical completion for the project originally set in the contract was 29 days.
Calculate the total extension of time that should be granted to the contractor for all applicable delays using the following methods:
The impacted as-planned method:
The collapsed as-built method:
The time impact method:
Transcribed Image Text:A completed project consisted of the following activities, many of which were delayed: Activity Predecessor Duration Delay Party at fauit A 8. Neutral B A 6. 3 4. Owner Neutral B. 3. 25 E D 12 Contractor A 6. Owner F 10 2 Owner The delays in the table above affected the start of each activity. Once each activity started, it took exactly the planned time in the table above for that activity to finish. The time for practical completion for the project originally set in the contract was 29 days. Calculate the total extension of time that should be granted to the contractor for all applicable delays using the following methods: The impacted as-planned method: The collapsed as-built method: The time impact method:
Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Linear Algebra: A Modern Introduction
Linear Algebra: A Modern Introduction
Algebra
ISBN:
9781285463247
Author:
David Poole
Publisher:
Cengage Learning