2. The following results were obtained from sieve analysis of sediment samples A and B. Hydrometer tests were conducted on the materials that passed through sieve 200 for Soils A and the ratio of clay to silt is 4:1. Plot the particle size distribution curves on the same graph. Determine the effective size d₁0, average sediment size d50, and compute for the gradation of the sediment mixture og and gradation coefficient Gr. Sieve No. Opening (mm) 4 10 20 40 100 200 pan 4.75 2.0 0.85 0.425 0.15 0.075 Mass retained (g) Sediment Sample A 0.0 20.2 25.7 40.4 18.1 27.2 68.2 Sediment Sample B 0.0 48.2 19.6 60.3 37.2 22.1 5.6

Principles of Geotechnical Engineering (MindTap Course List)
9th Edition
ISBN:9781305970939
Author:Braja M. Das, Khaled Sobhan
Publisher:Braja M. Das, Khaled Sobhan
Chapter4: Plasticity And Structure Of Soil
Section: Chapter Questions
Problem 4.8P
icon
Related questions
Question

The following results were obtained from sieve analysis of sediment samples A and B.
Hydrometer tests were conducted on the materials that passed through sieve 200 for Soils A
and the ratio of clay to silt is 4:1. Plot the particle size distribution curves on the same graph.
Determine the effective size d10, average sediment size d50, and compute for the gradation
of the sediment mixture σg and gradation coefficient Gr.

Sieve no. 4 10 20 40 100 200  pan
Opening (mm) 4.75 2.0 0.85 0.425 0.15 0.075  
Mass retained (g)              
Sediment sample A 0.0 20.2 25.7 40.4 18.1 27.2 68.2
Sediment sample B 0.0 48.2 19.6 60.3 37.2 22.1 5.6

 

2. The following results were obtained from sieve analysis of sediment samples A and B.
Hydrometer tests were conducted on the materials that passed through sieve 200 for Soils A
and the ratio of clay to silt is 4:1. Plot the particle size distribution curves on the same graph.
Determine the effective size d₁0, average sediment size d50, and compute for the gradation
of the sediment mixture og and gradation coefficient Gr.
Sieve No.
Opening (mm)
4
10
20
40
100
200
pan
4.75
2.0
0.85
0.425
0.15
0.075
Mass retained (g)
Sediment Sample A
0.0
20.2
25.7
40.4
18.1
27.2
68.2
Sediment Sample B
0.0
48.2
19.6
60.3
37.2
22.1
5.6
Transcribed Image Text:2. The following results were obtained from sieve analysis of sediment samples A and B. Hydrometer tests were conducted on the materials that passed through sieve 200 for Soils A and the ratio of clay to silt is 4:1. Plot the particle size distribution curves on the same graph. Determine the effective size d₁0, average sediment size d50, and compute for the gradation of the sediment mixture og and gradation coefficient Gr. Sieve No. Opening (mm) 4 10 20 40 100 200 pan 4.75 2.0 0.85 0.425 0.15 0.075 Mass retained (g) Sediment Sample A 0.0 20.2 25.7 40.4 18.1 27.2 68.2 Sediment Sample B 0.0 48.2 19.6 60.3 37.2 22.1 5.6
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Geotechnical Engineering (MindTap C…
Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning