The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job CR Job Due Date Duration (days) 103 103 214 10 205 205 223 309 309 217 11 412 219 412 517 216 15 517 Assume that all jobs arrived on day 180; today's date is 200.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged
as they arrived. All dates are specified as planning calendar days.
Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.)
Job
CR
Job
Due Date
Duration (days)
103
103
214
10
205
205
223
309
309
217
11
412
219
412
517
216
15
517
Assume that all jobs arrived on day 180; today's date is 200.
Transcribed Image Text:The following 5 overhaul jobs are waiting to be processed at Avianic's Engine Repair Inc. These jobs were logged as they arrived. All dates are specified as planning calendar days. Calculate the Critical Ratios (CR): (Enter all responses rounded to two decimal places.) Job CR Job Due Date Duration (days) 103 103 214 10 205 205 223 309 309 217 11 412 219 412 517 216 15 517 Assume that all jobs arrived on day 180; today's date is 200.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,